GENERAL EQUIPMENT INC.
8724 Sunset Drive #191● Miami FL 33173 · USA
|
LM2500
TYPE: |
Power |
DESCRIPTION: |
LM 2500 Turbine Gen Set 20 MW, 2nd Hand |
PRICE: |
Upon Request |
PACKING: |
Ex-Works |
lm 2500 turbine Gen set 20 MW
LM2500 set as follows;
1. Turbine – Steward & Stevenson – Aero-derivative Gas Turbine 2. Alternator – Frame BDAX7-16 7ES 3. Rated Voltage – 11kV 4. Maker – GE, USA 5. Installed Capacity – 20,000 6. Total Running Hours (since installed) – 22,214 hours 7. Total Running Hours (since overhaul) – 13,375 hours 8. Fuel Type – DIESEL 9. Lube Oil Type – Mobil Jet 2
GAS TURBINE GENERATOR SET SCOPE OF SUPPLY
|
TM2500
GE TM2500. We take pleasure in presenting our proposal on the GE TM2500’s . (Please see attached) These units are located in the USA and are available for immediate purchase (Two units are still available)
50/60HZ Mobile Gas Turbines
ITEM# QNTY DESCRIPTION 01 Two (2) New GE TM 2500 Plus (Mobile) 31MW, 60HZ, 13.8KV, 3 Phase, (Dual Fuel (26.1MW, 50HZ, 11.5KV) Can run on Natural Gas or Diesel Trailer Mounted Gas Turbine Generators available for immediate sale (Houston Texas) available for immediate delivery (Subject to prior sale)
The Trailer Mounted units are ideal as are designed for quick deployment, can be installed in less than a week if all infrastructure are in place. Please find attached GE Standard Brochure/ Fact sheet
TM 2500 MOBILE GAS TURBINE GENERATOR The TM2500 consist of two-trailer system with a top-mounted air inlet filter and exhaust assemblies, GE’s TM2500+ requires 77% less space than its predecessor. Both the inlet filter assembly and the Exhaust duct is mounted directly on top of the main trailer the units can easily transported by ship, air, or road to even the most remote locations around the globe. The improved TM2500+ design offers an increased number of quick-disconnect fittings, which simplifies and accelerates the installation process allowing for assembly and setup in just one day. The scope of each of these trailers will be described in detail.
Key Product Features and Benefits • Developed specifically to respond to the need for fast or mobile power • Small Footprint 24 m x 7 m (78 ft. X 21 ft.) • Flexible to operate on either natural gas or liquid distillate fuels • Dual Frequency—50/60 Hz quick conversion • Low emissions with demineralized water injection 25 ppm (gas)/42 ppm (liquid) • Quick to dispatch • Easy to operate and maintai |
2014 TM2500 Plus SAC Expected Maintenance
This document outlines the expected maintenance of the TM2500 Plus SAC Gas Turbine Package when operated in accordance with the OEM recommended procedures. The estimates provided below include maintenance of the TM2500 Plus SAC engine and periodic inspections of the turbine control system and auxiliaries.
Maintenance of the TM2500 Plus SAC Gas Turbine consists of periodic inspections and condition-based refurbishment of the engine. Routine maintenance as described in the Operations & Maintenance Manual is customer’s responsibility and not included in the price estimates provided below.
Periodic Inspections
Ø Borescope inspections of the engine are performed approximately every 4000 hours or annually, whichever comes first.
Ø An annual package inspection and controls calibration are also recommended and included in the estimates provided below.
Condition-based maintenance consists of the following:
Ø Hot Section & Combustor Rotable Exchange - Performed as appropriate in light of the operation and condition of the engine; expected to occur at approximately 25,000 fired hours of natural gas operation. The existing hot section and combustor modules will be removed, and refurbished replacement modules will be installed.
Ø Major Overhaul - Performed as appropriate in light of the operation and condition of the engine; expected to occur at approximately 50,000 fired hours. The engine will be removed from the plant site and taken to a GE overhaul depot for performance of the overhaul work. Key features of this overhaul are a complete tear down and inspection of engine and rebuilding with new or refurbished parts as required.
The maintenance described above will include parts, labor, and technical services for the Borescope and Package Inspections, Hot Section & Combustor Rotable Exchanges, and the Major Overhauls. Scheduled maintenance events from inspections to overhauls can be completed with minimum downtime; usually on weekends or other low demand periods (usually 1-5 days; assuming a Lease engine is used during overhaul).
See details at:
3xTM2500+ NewEquip Offer 032018_.pdf
Customer_Pitch_GE_Aero_TM_2500_August_2014.pdf
TM2500+ Mobile Gas Generator Fact Sheet.pdf
Specification and photos are not contractual and are subject to verification upon inspection
TAKE NOTICE!
PLEASE BE ADVISED THAT INFORMATION INCLUDED IS CONFIDENTIAL IN NATURE AND IS BASED ON PREXISTING BUSINESS RELATIONSHIP WITH THE LEGAL OWNER OF PROPERTY DESCRIBED HEREIN (IF APPLICABLE). AS SUCH, UPON RECEIPT OF SAID INFORMATION THE RECEIVER AKNOWLEDGES THAT ANY UNAUTHORIZED CONTACT WITH SAID LEGAL OWNER WILL BE CHARACTERIZED AS A BREACH OF CONFIDENTIALITY AND SAID AGREEMENT MAY BE ENFORCED UNDER EXISTING LAW OR IN EQUITY.
This paper was prepared by
General Equipment Corp.
The paper represents an offer of a partner of General Equipment Corp.
All rights are reserved by and for General Equipment Corp..
All
content and ideas of this paper are the property of General Equipment
Corp.